Current Projects
Hunter Rd Bridge (RIC-TR366-0.69) Monroe Township
Contractor: (Force Account)
19’0″x6’1″ Aluminum Box Culvert
Start Date: Sept. 15, 2025
Completion Date: Nov. 21, 2025
View Location
Armstrong Rd Bridge (RIC-TR113-0.67) Worthington Township
Contractor: (Force Account)
16’4″x5’11” Aluminum Box Culvert
Est. Start Date: July 21, 2025
Completion Date: Sept. 15, 2025
View Location
Townline Rd Bridge (RIC-TR79-4.19) Butler Township
Contractor: Crawford Construction (Contract Amount: $429,015.10)
Single Span Prestressed Concrete Box Beam
Start Date: June 2, 2025
Completion Date: August 14, 2025
View Location
Baseline Rd Bridge (RIC-CR11-9.97) Bloominggrove Township
Contractor: Crawford Construction (Contract Amount: $113,270.70) Furnish and Install Only
18’x6′ Concrete Box Culvert
Start Date: April 28, 2025
Completion Date: June 26, 2025
View Location
Coursen Rd Bridge (RIC-TR128-0.78) Perry Township
Contractor: R&I Construction (Contract Amount: $1,225,056.35)
Concrete I-Beam Bridge
Start Date: June 10, 2025
Completion Date: Sept. 12, 2025
View Location
Mock Rd Bridge (RIC-TR32-0.17) Perry Township
Contractor: V.O. Menuez & Son (Contract Amount $197,660.65)
14’8″x4’1″ Aluminum Box Culvert
Est Start Date: July 1, 2025
Completion Date: August 15, 2025
View Location